"Electrical Safety Accident Emergency Disposal and Investigation and Handling Regulations" Issuance

People's Daily, July 15. According to the Chinese government's website, the "Regulations on Handling and Investigation of Electric Safety Accidents" has been adopted by the State Council at its 159th executive meeting on June 15, 2011 and will come into effect on September 1, 2011. The regulations make it clear that the power company and its related personnel must not delay or report or report or report the accident. Any unit or individual must not intentionally destroy the scene of the accident and must not forge, conceal or destroy the relevant evidence.

The following is the full text of the Ordinance:

Regulations for Emergency Handling and Investigation of Electric Safety Accidents Chapter 1 General Provisions Article 1 These Regulations are formulated in order to strengthen the emergency handling of electric safety accidents, standardize the investigation and handling of electric safety accidents, and control, mitigate and eliminate electric safety accident damages.

Article 2 The term "electricity safety accidents" as mentioned in these Regulations refers to accidents that affect the safe and stable operation of the electric power system or affect the normal supply of electricity (including accidents affecting the normal supply of heat) that occur during the power production or power grid operation.

Article 3 According to the degree of electric safety accidents (hereinafter referred to as accidents) affecting the safe and stable operation of the electric power system or affecting the normal supply of electric power (heat), accidents are classified into special major accidents, major accidents, major accidents and general accidents. The standards for the classification of accidents are listed in the schedule of the Ordinance. If some items of the accident classification standard need to be adjusted, the State Council’s electricity regulatory agency shall propose a plan and report it to the State Council for approval.

The city where the provincial people's government is located, which is powered by a provincial power grid that is independent or through a single transmission line and connected to other provinces, and other cities or county-level cities that are powered by a single transmission line or a single substation, The standards for the classification of accidents causing power outages by power users shall be formulated separately by the State Council's power regulatory authority and reported to the State Council for approval.

Article 4 The State Council's power regulatory agencies shall strengthen the supervision and management of electric power safety, establish and improve various systems of accident emergency handling and investigation and disposal in accordance with the law, and organize or participate in the investigation and handling of accidents.

The State Council's power regulatory agencies, the State Council department in charge of energy, and other relevant departments of the State Council, local people's governments and relevant departments shall organize, coordinate, and participate in the emergency handling of accidents in accordance with the authority and procedures prescribed by the State.

Article 5 Electric power enterprises, electric power users and other relevant units and individuals shall abide by the regulations on electric power safety management and implement accident prevention measures to prevent and avoid accidents.

The important power users determined by the relevant departments of the local people's governments at or above the county level shall, in accordance with the provisions of the State Council's power regulatory agency, configure their own emergency power supply and strengthen the management of safe use.

Article 6 After an accident occurs, the power company and other relevant units shall, in accordance with the provisions, report the accident in a timely and accurate manner, carry out emergency handling work, prevent the accident from expanding, and reduce the damage caused by the accident. Power companies should restore power production, power grid operation and normal supply of electricity (heat) as soon as possible.

Article 7 No unit or individual may obstruct or interfere with the reporting of accidents, emergency handling, or investigation and handling according to law.

Chapter II Accident Report Article 8 After an accident, the relevant personnel at the scene of the accident shall immediately report to the on-duty personnel of the power plant, substation operation, on-duty personnel of the power dispatching agency, or on-site person in charge of the company. After the relevant personnel receive the report, they shall report immediately to the power dispatching agency and the responsible person of the company. After receiving the report, the person-in-charge of the company shall report immediately to the local electric power regulatory agency located in the local dispatched organization (hereinafter referred to as the electric power supervision agency in the place where the accident occurred) and the safety production supervision and management department of the people's government at or above the county level; the thermal power plant accident impact heat is normal. The supply shall also be reported to the heating management department; where the accident involves the dam safety of the hydropower plant (station), it shall also report to the competent water administrative department or the river basin management agency.

The power company and its related personnel shall not delay or report or report or report the accident.

Article 9 After receiving the accident report, the power regulatory agency shall immediately verify the relevant situation and report it to the power regulatory agency of the State Council. If the power supply user of the accident causes a blackout, it shall also notify the local people's government at or above the county level where the accident occurred.

For special major accidents and major accidents, the State Council’s power regulatory agency shall report to the State Council immediately after receiving the accident report, and shall notify the relevant departments of the State Council’s production safety supervision and administration department and the State Council’s energy authority.

Article 10 The accident report shall include the following contents:

(1) The time, place (region) and accident-occurring unit of the accident;

(2) Known conditions of damage to power equipment and facilities, the number of generating units that are out of service (heating), the number of power grids that reduce the supply of power, or the number of power plants that reduce their output, and the power outage (stoppage of heat) range;

(3) The preliminary judgment of the cause of the accident;

(4) Measures taken after the accident, the operation mode of the power grid, the operation status of the generator set, and the accident control situation;

(5) Other circumstances that should be reported.

If a new situation arises after the accident report, it shall be reported in a timely manner.

Article 11 After an accident occurs, the relevant units and personnel shall properly protect the accident site and related materials such as working logs, work tickets, and operation tickets, and timely save the fault recorder, power dispatch data, generator set operation data, and power transmission and transformation equipment. Operational data and other relevant data, and after the establishment of the accident investigation team, related materials and data will be transferred to the accident investigation team.

In case of rescue personnel or emergency measures such as restoration of power production, power grid operation and power supply, etc., where the accident site or mobile power equipment needs to be changed, a mark shall be made, a sketch map shall be made, important traces and physical evidence shall be properly kept, and a written record shall be made.

No unit or individual may intentionally destroy the scene of the accident and must not forge, conceal or destroy the relevant evidence.

Chapter III Emergency Response to Incidents Article 12 The State Council's power regulatory agency organizes and compiles national emergency plans for large-scale blackouts of power grids in accordance with the "Law of the People's Republic of China on Incidents Response" and the "National Overall Emergency Preparedness for Public Incidents". State Department approved.

The local people's government concerned shall, in accordance with laws, administrative regulations, and emergency plans for the country's large-scale power outages in case of power grids, organize the formulation of contingency plans for handling large-scale blackouts of power grids in this administrative region.

The emergency plan for handling large-scale power outages in power grids shall provide specific provisions for emergency organization and command systems and responsibilities, measures for emergency response, and emergency protection for personnel, funds, materials, and technology.

Article 13 An electric power enterprise shall, in accordance with the relevant provisions of the State, formulate its own accident emergency plan.

The power regulatory agency shall guide the power companies in strengthening the construction of emergency rescue teams and improve the emergency material reserve system.

Article 14 After an accident occurs, the relevant power company shall immediately take appropriate emergency measures to control the scope of the accident and prevent the system from collapsing and disintegrating. If the accident threatens the safety of people and equipment, the power plant and substation personnel on duty may follow. Relevant regulations immediately take emergency measures such as stopping generator sets and power transmission and transformation equipment.

Where an accident causes damage to electrical equipment or facilities, the relevant power company shall immediately organize a repair.

Article 15 According to the specific conditions of an accident, the power dispatching agency may issue power dispatching orders such as turning on or off the generator set, adjusting the active and reactive load of the generator set, adjusting the power grid operation mode, adjusting the power supply dispatching plan, and the power generation enterprise and the power user. Should be implemented.

The accident may lead to the destruction of the power system and the large-scale power outage of the power grid. The power dispatching agency has the power to decide on the necessary measures such as pulling the load, de-listing the power grid, and disassembling the generator set.

Article 16 If an accident causes a large-scale power outage of the power grid, the State Council’s power regulatory agency and other relevant departments of the State Council, relevant local people's governments, and power companies shall, in accordance with relevant state regulations, initiate corresponding emergency plans, establish emergency command agencies, and resume power grid operations as soon as possible. And electricity supply to prevent the occurrence of various secondary disasters.

Article 17 Where an accident causes a power outage in a large area of ​​the power grid, the relevant local people's government and relevant departments shall immediately organize the following emergency disposal work:

(1) Strengthen the security protection of key units in the blackout regions related to the national economy, people's livelihood, national security and public safety, guard against acts that undermine social order, and maintain social stability;

(2) to eliminate in time the various dangers that occur due to power outages;

(3) If an accident results in heavy casualties or if an emergency transfer or resettlement of a trapped person is required, the organization shall timely organize the implementation of treatment, transfer, and resettlement;

(4) Strengthen road traffic command and guidance in power blackout areas, and do a good job in railway and civil aviation transportation and communication security;

(5) Organize the emergency production and invocation of emergency supplies to ensure the supply of necessary materials for the restoration of the power grid and the basic living materials of residents.

Article 18 Where an accident causes the interruption of power supply to an important power user, an important power user shall quickly start the self-contained emergency power supply in accordance with the relevant technical requirements; if the self-prepared emergency power source is not effective, the power grid enterprise shall provide the necessary support.

Where an accident causes a power outage at a crowded place such as a subway, airport, high-rise building, shopping mall, theater, sports stadium, etc., the emergency lighting shall be promptly activated and the personnel shall be evacuated in an orderly manner.

Article 19 To restore power grid operation and power supply, priority shall be given to ensuring the restoration of power plant power supplies, important power transmission and transformation equipment, and electric backbone grids of major power plants, and priority shall be given to restoring the power supply of important power users, important cities, and key areas.

Article 20 The accident emergency commanding agency or the power regulatory agency shall, in accordance with relevant regulations, issue unified, accurate and timely information on the scope of the accident, the progress of the disposal, and the expected time for restoration of the power supply.

Chapter IV Accident Investigation and Treatment Article 21 The special accidents shall be investigated by the accident investigation team of the State Council or a department authorized by the State Council.

The major accidents were organized by the State Electricity Regulatory Authority to organize an accident investigation team to investigate.

Large accidents and general accidents were investigated by the electric power supervision agency organized by the accident investigation team. If it is deemed necessary by the power regulatory agency of the State Council, an accident investigation team may be organized to investigate major accidents.

In the event of a general accident that does not result in a blackout of the power supply user, the power regulatory agency that has caused the accident may also entrust the accident-producing agency to investigate and handle it.

Article 22 According to the specific circumstances of the accident, the accident investigation team shall be composed of electric power regulatory agencies, relevant local people's governments, safety production supervision and management departments, and relevant departments with the responsibility for safety production supervision and management; related personnel shall be suspected of negligence or dereliction of duty. Or suspected of committing a crime, it shall invite supervisory organs, public security organs, and people's procuratorates to send people to participate.

According to the needs of the accident investigation work, the accident investigation team may employ relevant experts to assist in the investigation.

The head of the accident investigation team is appointed by the organization of the accident investigation team.

Article 23 The accident investigation team shall carry out an accident investigation in accordance with the relevant regulations of the State, and submit an accident investigation report to the organization organizing the accident investigation team within the following time limit:

(1) The investigation period for special major accidents and major accidents shall be 60 days; under special circumstances, the approval of the organization of the accident investigation team may be extended as appropriate, but the extension period must not exceed 60 days.

(2) The investigation deadline for major accidents and general accidents is 45 days; under special circumstances, the approval of the organization of the accident investigation team may be extended as appropriate, but the extension period must not exceed 45 days.

The accident investigation period is calculated from the date of the accident.

Article 24 The accident investigation report shall include the following contents:

(1) Overview of accident-producing units and accidents;

(2) The direct economic loss caused by the accident and the impact of the accident on the normal operation of power grid operation and electricity (thermal power);

(c) the cause of the accident and the nature of the accident;

(4) Emergency handling of accidents and restoration of power production and power grid operation;

(5) Accident liability determination and handling suggestions for responsible units and responsible persons;

(6) Accident prevention and rectification measures.

The accident investigation report shall be accompanied by relevant evidence and technical analysis reports. Accident investigation team members should sign the accident investigation report.

Article 25 The accident investigation report is submitted to the organization of the accident investigation team of the organization and the accident investigation work is completed; the general accidents investigated by the commissioned accident investigation unit shall be reported to the electric power regulatory agency at the place where the accident occurred.

The relevant agencies shall punish the unit where the accident occurs and related personnel in accordance with the law, and impose sanctions on the state staff responsible for the accident.

The accident-producing entity shall handle the personnel responsible for the accident in this unit.

Article 26 The accident-producing unit and relevant personnel shall seriously learn lessons from accidents, implement accident prevention and rectification measures, and prevent accidents from occurring again.

The electric power regulatory agencies, safety production supervision and management departments, and relevant departments with the responsibility for safety production supervision and management shall supervise and inspect accident-prevention units and related personnel in the implementation of accident prevention and rectification measures.

Chapter V Legal Liabilities Article 27 If the main responsible person of an electric power enterprise having an accident commits one of the following acts, the electric power regulatory agency shall impose a fine of 40% to 80% of the previous year's annual income; if it belongs to a national staff member, And to be given a punishment according to law; if it constitutes a crime, criminal responsibility shall be investigated according to law:

(1) Failure to immediately organize an accident to rescue;

(2) Delaying or failing to report the accident;

(3) Abandoning duties during the accident investigation and handling.

Article 28 If an electric power company and its related personnel who have an accident commit one of the following acts, the electric power regulatory agency shall impose a fine of not less than 1 million but not more than 5 million yuan on the electric power enterprise; the main responsible person and the person directly in charge shall be responsible for it. And other directly responsible personnel shall be imposed a fine of 60% to 100% of the previous year's annual income and shall be punished according to law if they fall into the category of national staff; if it constitutes a violation of public security administration, public security organs shall impose penalties for public security administration according to law; , investigate criminal responsibility according to law:

(1) misrepresenting or reporting an accident;

(2) Forging or deliberately destroying the scene of the accident;

(3) to transfer or conceal funds or property or destroy relevant evidence or data;

(4) Refusing to accept the investigation or refuse to provide relevant information and information;

(5) Making perjury in an investigation of an accident or instructing another person to commit perjury;

(6) To escape after the accident.

Article 29 If a power company is responsible for the accident, the power regulatory agency shall impose a fine in accordance with the following provisions:

(1) Where a general accident occurs, a fine of 100,000 yuan up to 200,000 yuan shall be imposed;

(2) If a major accident occurs, a fine of 200,000 yuan up to 500,000 yuan shall be imposed;

(3) Where a major accident occurs, a fine of 500,000 yuan up to 2 million yuan shall be imposed;

(4) Where a special major accident occurs, a fine of 2 million yuan up to 5 million yuan shall be imposed.

Article 30 If the main responsible person of a power company fails to perform the duties of safety production management in accordance with the law, resulting in an accident, the power regulatory agency shall impose a fine in accordance with the following provisions; if it belongs to the national staff, it shall be punished according to law; if it constitutes a crime, it shall be prosecuted according to law. responsibility:

(1) If a general accident occurs, a fine of 30% of the previous year's income shall be imposed;

(2) If a major accident occurs, a fine of 40% of the previous year's annual income shall be imposed;

(3) Where a major accident occurs, a fine of 60% of the previous year's income shall be imposed;

(4) If a special major accident occurs, it shall be imposed a fine of 80% of the previous year's annual income.

Article 31 Where a person in charge of a power company is dismissed from a position or imposed criminal punishment in accordance with the provisions of Articles 27, 28, and 30 of these Regulations, it shall be subject to the day of punishment or the completion of execution of the penalty. Within 5 years, it shall not be the principal person in charge of any production and business unit.

Article 32 Where any of the following acts is committed by the power regulatory agency, the local people's government concerned, and other relevant departments that have the responsibility for supervision and administration of production safety, the person directly in charge and other directly responsible personnel shall be given sanctions; directly responsible; If a person in charge or other directly responsible person commits a crime, he shall be investigated for criminal responsibility according to law:

(1) Failure to immediately organize an accident to rescue;

(2) Delaying, failing to report, or reporting or misrepresenting an accident;

(3) Obstructing and interfering with the accident investigation work;

(4) Making perjury in an accident investigation or instructing another person to make false testimony.

Article 33 If the personnel involved in the accident investigation have one of the following acts in the accident investigation, they shall be disciplined according to law; if the crime is constituted, criminal responsibility shall be investigated according to law:

(1) Being irresponsible for accident investigation work, resulting in major omissions in accident investigation work;

(2) Protecting or protecting those responsible for accidents or taking the opportunity to fight revenge.

Chapter 6 Supplementary Provisions Article 34 The occurrence of an accident as prescribed in these Regulations and causing casualties or direct economic losses at the same time shall be different from the accident levels determined in accordance with the Regulations for the Reporting and Investigation of Production Safety Accidents. Anyone who has a higher accident grade determines the grade of the incident and investigates and deals with it in accordance with the provisions of this Regulation. If the accident causes casualties, it constitutes a major accident or a particularly serious accident as stipulated in the “Regulations on the Reporting and Investigation of Production Safety Accidents”, in accordance with the "Accident report and investigation and handling regulations" stipulates investigation and handling.

In the event that power generation equipment or power grid equipment is damaged during the power generation or power grid operation, resulting in direct economic loss accidents, without affecting the safe and stable operation of the power system and the normal supply of electricity, the power regulatory agency shall report and investigate the production safety accident according to the The provisions of the Regulations constitute an accident investigation team to investigate major accidents, major accidents, and general accidents.

Article 35 Where there is no provision for accident reporting and investigation and handling in this Regulation, the provisions of the "Regulations on the Reporting and Investigation of Production Safety Accidents" shall apply.

Article 36 The emergency handling and investigation and handling of nuclear accidents in nuclear power plants shall be implemented in accordance with the Regulations for the Emergency Management of Nuclear Accidents in Nuclear Power Plants.

Article 37 This Regulation shall come into force on September 1, 2011.